Replacement of Berth 8

  • Owner:  North Carolina State Ports Authority
  • Construction Cost: $16,100,000
  • Completion Date:  March 2010

Scope of Services:

  • Complete Demolition of Existing Berth
  • Construction of New Berth Complete with Fender System

Replacement of Berth 8 in Wilmington, NC for NCSPA: Demolition and removal of existing pile supported Berth 8 structure (83,145 Sq. Ft.); construction of new pile supported wharf structure (83,880 Sq. Ft.), and installation of new fender systems, mooring hardware, crane tie downs, crane rail, railroad railing, and miscellaneous utilities on the new wharf structure at the Wilmington Terminal.