Project Description
EC Source subcontracted Cape Romain Contractors to build four pile supported foundations for new power transmission lines across the Stono River. Crews will install four (4) pile and cap reinforced concrete foundation structures and will frame and set four (4) galvanized steel power poles on the new foundations. After completion, Cape Romain will remove existing towers and foundations.
Scope of Services
- Installation of 32 each 18” PSC Piles
- Cast in place power pole foundations (22’x10’)
- Anchor bolts
- Assist in installation of galvanized steel power poles
Details
Owner:
Dominion Energy Transmission Line Foundation
Cost:
$1,161,400
Location:
Completion Date:
May 2023 estimated